WHICH TYPE OF RELATIONSH IIP DENOTES THE DEPENDENCE, IN WHICH THE TASK B CAN NOT FINISH UNTIL THE TASK A IS FINISHED Bbl6epuTe OAMH OTBeT: a. start-to-finish b. Start-to-start c. finish-to-finish d. finish-to-start

Решения

4.6 (248 Голоса)
Яромир
Экспертная проверка
элита · Репетитор 8 лет

Ответ

The correct answer is 'd'.

Объяснение

## Step 1The problem is asking us to identify the type of relationship that denotes a situation where task B cannot be completed until task A is finished. This is a concept in project management, where tasks are often dependent on each other.## Step 2The options provided are:a. start-to-finishb. start-to-startc. finish-to-finishd. finish-to-start## Step 3The correct answer is "finish-to-start". This is because in a "finish-to-start" relationship, task B cannot start until task A is finished. This is the exact situation described in the problem.