WHICH TYPE OF RELATIONSH IIP DENOTES THE DEPENDENCE, IN WHICH THE TASK B CAN NOT FINISH UNTIL THE TASK A IS FINISHED Bbl6epuTe OAMH OTBeT: a. start-to-finish b. Start-to-start c. finish-to-finish d. finish-to-start
Решения
4.6248 голоса

Яромир
Экспертная проверка
элита · Репетитор 8 лет
Отвечать
The correct answer is 'd'.
Изложение
## Step 1<br />The problem is asking us to identify the type of relationship that denotes a situation where task B cannot be completed until task A is finished. This is a concept in project management, where tasks are often dependent on each other.<br /><br />## Step 2<br />The options provided are:<br />a. start-to-finish<br />b. start-to-start<br />c. finish-to-finish<br />d. finish-to-start<br /><br />## Step 3<br />The correct answer is "finish-to-start". This is because in a "finish-to-start" relationship, task B cannot start until task A is finished. This is the exact situation described in the problem.